Nortex Modular Space

 


 


      

      

 

City of Houston Daily Reports

 

Project:  City of Houston Airport

Project Manager:   Mike Lodes

 

Date: April 11,  2006

Weather: Cloudy to very Moderately Sunny  55 high 80 moderate to gusty winds 

Personnel / Subcontractors on site:

Nortex Modular Space: PM Mike Lodes

Objective:

Site visit to inspect drilled piers. (Customer questioned pier inspectability) and to make contact with customer to expedite approval process.

Status:

Piers ready for inspection. Some piers have water left inside.

Gave Jamie wind load information. I was informed that building permit would be available in 3 to 4 weeks.

 

 

Date: April 13,  2006 - transfer upload ACAD files to customer ftp: site/ Download pictures/ Email Correspondence

 

Date: June 06, 2006

Weather:  part sunny 74 to 93 degrees very warm

Personnel on Site:

Objective:

(1) To have EE Design furnish City with updated Struct plan.

Status @ EOD:

(1) N/A.

Issues:

Overview:

Awaiting permits before installation.

 

Date: June 06, 2006

Weather:  part sunny 74 to 93 degrees very warm

Personnel on Site:

Objective:

(1) To have EE Design furnish City with updated Struct plan.

Status @ EOD:

(1) N/A.

Issues:

Overview:

Awaiting permits before installation



Date: June 07, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To have EE Design furnish City with updated Struct plan.

(2) Call directly to Arch/Engineer for status.

Status @ EOD:

(1) N/A.

(2) Spoke with Harvey (EE's Architect) as I discovered that he

     had drawn the building out of scale which appeared out of

     proportion to the City. I have given the correct dimensions

     to be re-drawn and I have been promised that the revised

     sealed plan will be available for Valerie to pick-up and hand

     carry it to the city. Only one sheet has to be revised and re-sealed.

Issues:

Overview:

Awaiting permits before installation.

 

 

Date: June 08, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To have Jamie ok the delivery of the buildings to the site.

Status @ EOD:

(1) Left message

Issues:

Overview:

Awaiting permits before installation.

Valerie mentioned the delivery ergency

to Jamie already once.

 

 

Date: June 09, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To have Jamie ok the delivery of the buildings to the site.

 Status @ EOD:

(1) Left message

Issues:

Overview:

Awaiting permits before installation.

Valerie mentioned the delivery ergency

to Jamie already once.

 

Date: June 13, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To inform Jamie of the delivery time of the buildings to the site on Wednesday the 14th.

(2) Issue P.O. to Allstate for delivery.

Status @ EOD:

(1) Jamie Salinas is aware of the buildings arriving tomorrow the 14th

      and will take measures to clear parking lot for temp location.

(2) Barb issued the P.O. and Allstate confirmed delivery and contact info.

Issues:

Overview:

Awaiting permits before installation.

Valerie mentioned the delivery ergency

to Jamie already once.


 

Date: June 14, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To inform Jamie of the delivery time of the buildings to the site on Wednesday the 14th.

(2) Contact with factory as of when bldg's are picked up.

Status @ EOD:

(1) Jamie Salinas is aware of the buildings arriving today

      and will take measures to clear parking lot for temp location.

(2) Bldg's were being signed off at the factory by Allstate drivers

      at 8:30 am this morning.

Issues:

Overview:

Awaiting permits before installation.

Estimated Installation Window:  Footing pour - July 8

                                                      BLAS           - July 15 thru 20

                                                      Stucco          - July 21 thru 28

                                                      Conc            - by Aug.4th

 

 

 

Date: June 15, 2006

Weather:  N/A

Personnel on Site:

Objective:

(1) To confirm with Jamie the delivery of the buildings to the site on Wednesday the 14th.

Status @ EOD:

(1) Jamie Salinas has received the buildings.

Issues:  Broken pane in one window
Overview:

Awaiting permits before installation.

First on list and should have word on permit

by Friday the 16th.

 Estimated Installation Window:  Footing pour - July 8

                                                      BLAS           - July 15 thru 20

                                                      Stucco          - July 21 thru 28

                                                      Conc            - by Aug.4th

 

 

 

Nortex Modular Space
555 Jubilee Lane
Lewisville, TX 75056
Phone 972-492-4040/Fax 972-492-2704
www.nortexmodular.com

GSA prefabricated buildings, and modular church buildings