| In the fall of 2001, the Reserve Air Command ordered a 56' x 112' modular
office building for its Fort Hood operations. The building featured a
poured-in-place concrete foundation, stucco exterior, nine foot interior
ceiling, fire-rated commerical interior finishes, fire alarm system, telcom
wiring, fibre-cement subfloor, commerical grade fixtures, handicap restrooms and
poured-in-place concrete decks, ramps and landings. The project was completed in
the spring of 2002.

|
|